What should happen with Product Backlog Items that were selected for the Sprint
but which by the end of the Sprint do not meet the Definition of Done?
[A] Should be put back in the Product Backlog
[B] New Product Backlog Items should be created for the remaining work
[C] Should not be part of the Product Increment
[D] Should be reviewed during the Sprint Review meeting
[E] The Product Owner still can decide to accept the work and release it